Open site navigation
Explore Comal.News
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County news deskLocal reporting, every day

What do Coll Street’s two funding figures tell residents?

Coll Street construction has begun, and drivers and nearby businesses face phased access changes through early 2028.

Listen to this articleComal.News narrated edition
Ready · 0:00 / 5:02
Two blank placards stand beside a stylized road construction area with drainage pipes, barriers, shrubs and an unmarked signpost.
Illustration: Blank placards beside a road and drainage construction scene evoke the funding figures and street work discussed in the article.Original editorial illustration; not a photograph and does not depict the reported event or an exact property.Comal.News Visual Desk · Original illustration · Source ↗ · Comal.News original illustration ↗

Coll Street’s $7.2 million economic-development approval in 2024 now sits beside an approximately $8.2 million city portion of a joint construction project.

In March 2024, the city said council approved $7.2 million in NBEDC funding for Castell Avenue Phase 1 and Coll Street drainage between Castell Avenue and the Comal River. The March 2024 city announcement focused on storm-drain improvements.

From the source record

City project noticeColl Street drainage improvement project
The city describes drainage, utility, roadway and pedestrian work between Castell Avenue and the Comal River.
City of New Braunfels ↗
Summary of the city’s October 2026 project notice; this is a document graphic, not a photograph of the work.

Drivers and nearby businesses face phased access changes as Coll Street work continues toward early 2028. The October 2026 construction notice describes the current project and schedule.

What it costs

The city’s October 2026 release puts the joint city and New Braunfels Utilities construction project at $9.6 million and calls the city’s portion approximately $8.2 million, funded by NBEDC. Those labels matter: the earlier number is an approval for economic-development funding, while the later one describes the city’s approximate share of a joint construction project.

Three public figures for Coll Street, 2024–2026; the figures describe different measures
FigureAmountStatus and scope
2024 NBEDC funding$7.2 millionCouncil approval for Castell Avenue Phase 1 / Coll Street drainage
2026 city portionAbout $8.2 millionCity-described portion of joint construction project, funded by NBEDC
2026 joint project$9.6 millionCity and NBU construction project

The 2024 approval and 2026 approximate city portion are differently described measures; the table does not establish spending, a cost overrun or NBU’s contribution.

A Comal.News comparison of those releases puts the difference between the 2024 approval and the current approximate city portion at about $1 million. Because one figure is a 2024 approval and the other is an approximate 2026 city portion, that difference alone cannot establish an overrun or spending. It also cannot be used to calculate NBU’s exact contribution to the joint project.

Who pays and who benefits

The city describes storm-drain work, utility upgrades, roadway work, sidewalks, landscaping and conversion of overhead utilities to underground lines between Castell Avenue and the Comal River. The stated city portion draws on NBEDC funding. Residents and businesses along the route would receive the finished street and drainage work, while phased construction changes access in the meantime.

What has to go right

Pesado Construction is the contractor, and the city says construction has begun. The city expects phased work through early 2028. That schedule makes the construction phases as important to nearby businesses and drivers as the final improvements: access can change before the finished drainage, road and sidewalks are in place.

What the next records can settle

The useful comparison is between like measures: the work covered by the 2024 funding approval and the work and financing in the executed construction contract. A contract, any amendments and the NBEDC authorization and payment ledger would let readers distinguish an added commitment from money already paid. Until those figures can be matched by scope and status, the roughly $1 million difference is a question to investigate, not a bill attributed to a particular change. Readers can inspect the city’s 2024 funding announcement and its current construction notice to see the two descriptions directly.

Related coverage

The Comal Daily

Comal County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.