Nearly $700,000 in development-paid road fees will rebuild Gruene Road at Post Road, but the first thing existing drivers get is construction delay.
Drivers are expected to encounter delays from the Nov. 2 start, with the first detour expected around early December. The city expects work to run into mid-February, subject to weather and other factors. Its city's Oct. 28 project notice says the initial phase is not expected to require a detour.
From the source record
Work is scheduled to start November 2 and continue into mid-February, subject to weather and other factors.City of New Braunfels ↗
The city's roadway impact fee rules assess fees at platting and collect payment when a building permit is sought. The city says road impact fees from new development will fund the project. That connects a charge tied to new building with work at an intersection used by existing road users; the announced price describes the project, not a per-household bill.
What the money buys
The city plans to realign Gruene Road at Post Road, install a four-way stop, add sidewalks and ADA-compliant curb ramps, and complete striping and minor drainage work. The city describes better safety and less congestion as goals for the redesigned intersection. Those are intended results; the construction list alone cannot measure them.