The presentation also projects 2.9 acres of permanent drainage easements. That figure describes another anticipated land need. Neither acreage figure says every parcel has already changed hands.
TxDOT anticipates no residential displacement and proposes no noise barriers. The nine-business figure is likewise a projection: it identifies possible displacement under the design, not nine announced closures.
A large state plan and a local funding gap
TxDOT announced a $138 billion statewide transportation plan for 2027. The statewide figure combines money for projects with development and routine maintenance; it is not a construction award for this corridor. The U.S. 281 project materials still identify no construction funding.
Source: TxDOT's statewide transportation announcement. These totals do not assign construction funding to the South Comal U.S. 281 project.
Think about the two figures separately. A statewide program can pay for planning and other preparatory work even when a particular road lacks money to build it. For a driver, the number that changes the timetable is a project-specific construction allocation, not the statewide total.
The travel-time promise is still a forecast
TxDOT counted 404 crashes on the corridor from 2021 through 2025, including 101 injury crashes and one fatal crash. Those are observed past incidents, separate from the agency's predictions about future traffic.
For 2049, TxDOT's model projects a 47-minute northbound afternoon trip without the expansion and seven minutes with it. That is a comparison between modeled futures, not time saved by a road that has already been built. It shows why the design could matter greatly to drivers if the project reaches construction.
The trade-off is a timing one. Land acquisition and possible business displacement may arrive first. The modeled travel-time improvement depends on later review, design, utility work and construction funding. The proposal puts those consequences on the same map, but not on the same calendar.
What to watch next
TxDOT expects an environmental decision in 2027. Public comments on the proposal are due by 11:59 p.m. Nov. 25. The decision, subsequent acquisition records and any construction allocation will show how far the project moves beyond its current design.
Residents can inspect the project presentation for the proposed footprint, modeled traffic and comment instructions. The next number to watch is a construction allocation for U.S. 281 itself.