TxDOT estimates about $354 million for a proposed U.S. 281 expansion in south Comal County, but it has identified no construction funding. What does the statewide plan buy here?
Texas' 2027 Unified Transportation Program includes $95 billion for projects over 10 years, while TxDOT's release puts another $43 billion in development and routine maintenance in its $138 billion projected transportation total. Those are statewide program figures; the separate local hearing presentation puts a construction estimate on this particular stretch.
Map from the record

From the record

For drivers on this stretch of U.S. 281, construction depends on environmental review, final design, right-of-way, utility coordination and funding. The distinction is simple: a cost estimate describes the project, while identified construction funding would establish a way to pay for that work.
Where and when
The places and times below come from the official pages linked with each one.
- Site
Proposed U.S. 281 project corridor
US 281 from East Borgfeld Drive to SH 46
Proposed project corridor
What does the statewide figure mean here?
The state announcement describes a 10-year transportation program. The hearing presentation describes a 6.7-mile proposal from East Borgfeld Drive to State Highway 46 and gives its own estimated construction cost. Reading the statewide total as this project's budget would skip the step TxDOT itself identifies: finding construction funding for the local job.
Our earlier report on the statewide plan and the local comment deadline covered the two announcements together. The useful follow-up question is narrower: what would have to happen before work begins on this corridor? TxDOT's project page lists the remaining reviews and coordination, and the hearing slide identifies funding as another condition.