Open site navigation
Explore Comal.News
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County news deskLocal reporting, every day

NBU budgets land first for $1.9 million FM 1044 water-main plan

Residents near FM 1044 now have a planned route and July 2029 target for a new water main. NBU's approved FY2027 budget puts $87,613 toward it; later spending remains a projection.

Blue water pipe beside a folded map with a rust-colored dotted route and pin, surrounded by sparse grass.
A water pipe beside a map suggests the planned FM 1044 main; it does not depict construction.Illustration: Comal.News

NBU plans a roughly 5,000-foot water main along FM 1044, and its approved FY2027 budget assigns $75,000 to land and easements.

The FY2027–FY2031 capital plan describes a 12-inch line between Michelson Lane and Green Valley Road. The first year's project budget is $87,613. NBU projects nearly $2 million across five fiscal years and lists July 31, 2029, as the target completion date. Only FY2027 is appropriated in this plan; the later figures are planning estimates subject to future review and approval.

Land and easements dominate the FM 1044 line's first-year budgetProjected FY2027 dollars by cost category
Source: New Braunfels Utilities FY2027–FY2031 Capital Improvement Plan, project 2-C271044W.
Map

Where and when

The places and times below come from the official pages linked with each one.

  • Site

    FM 1044 water-main extension

    FM 1044 between Michelson Lane and Green Valley Road

    Target completion July 31, 2029

    Planned 12-inch water-main extension

    Source: New Braunfels Utilities ↗

What the plan commits

The board approved the FY2027 capital budget on June 25, 2026. That approval puts the project's first-year amount in the budget. It does not turn the larger, five-year projection into a signed construction contract.

For residents near the Michelson Lane–Green Valley Road stretch, NBU's plan identifies where a new 12-inch water main would run. The project page calls it “WTR - Distribution Main - FM 1044 - System Extension” and assigns it project number 2-C271044W. Those identifiers give residents a way to follow later engineering, property and purchasing records for this particular line.

Where the money lands

NBU projects $87,613 in FY2027, about $1.26 million in FY2028 and $574,920 in FY2029, with no project spending listed in FY2030 or FY2031. Look at the FY2028 row: the largest year of projected spending comes after the approved first-year budget.

NBU's projected FM 1044 water-main spending by fiscal year, FY2027–FY2031
Fiscal yearProjected spending
FY2027$87,613
FY2028$1,257,627
FY2029$574,920
FY2030$0
FY2031$0

Source: NBU FY2027–FY2031 Capital Improvement Plan, project 2-C271044W. Only FY2027 is appropriated in this plan.

The FY2027 breakdown is $75,000 for land and easements, $2,250 for internal labor, $1,749 for engineering and $8,614 for overhead. The plan also projects $1.4 million in contract labor over five years. A projected cost category shows how NBU expects to spend money; it does not name a contractor or establish an award.

What “growth” means here

NBU labels the line “System Extensions (Growth)” and “New Capital.” In this plan, those are classifications for a new distribution-main project. They do not identify a development or promise a connection to a particular property.

The next record to watch

The July 31, 2029 target is a schedule in the capital plan, not a completion notice. A later design, easement filing, budget approval or construction award would make the route, funding and timing more concrete. Residents can use project 2-C271044W in NBU's capital plan to check the current scope and compare it with those later records.

The Comal Daily

Comal County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.