ERCOT got 433 of 465 data-center questionnaires back, but the water answers inside them are less complete. That is the puzzle behind Texas’ early account of what proposed data centers could demand from their neighbors.
The 93% return rate tells Texans how many developers replied. ERCOT’s preliminary figures give a different answer when the question is whether a reply supplied a usable value for water or cooling. For residents weighing a project near their water supply, those are the figures to watch.
What does 93% count?
ERCOT’s inquiry reaches developers seeking an interconnection of at least 25 megawatts for a data center. It asks about electricity, water, cooling and other effects on nearby communities. A returned form is therefore a useful first step, but the return rate alone says nothing about how many answers contain a value.
ERCOT's preliminary analysis describes about 177 gigawatts of requested interconnection capacity, not electricity already being used. In the regional breakdown, 429 loads account for that requested capacity. The West zone has the largest share, at 73 gigawatts; South has 49, North 45 and Houston 10. ERCOT assigned zones from project coordinates and cautioned that a project’s eventual interconnection zone may differ.
Map from the record

Those numbers describe a queue of requests, not a reading from power plants or water meters. They establish where developers have asked for grid access in ERCOT’s preliminary analysis. They do not measure water actually consumed.