ERCOT targets Dec. 10 report on data-center impacts Comal County raised

Comal County residents now have a Dec. 10 checkpoint for a state report on data-center water use and other impacts. ERCOT has received 433 responses to its inquiry.

Listen to this articleHear this story read aloudComal.News narrated edition
Ready · 0:00 / 3:06
An open blue folder with blank pages and a water droplet symbol floats above an empty room of curved desks and monitors.
A report marked with a water droplet hangs above a stylized grid control room, representing the inquiry into data-center impacts.Illustration: Comal.News

ERCOT has received 433 responses to its statewide data-center impact inquiry and is targeting Dec. 10 for a public report.

Comal County commissioners approved Resolution 2026-12 by a 4–1 vote on May 14, asking the state to examine the effects of additional data centers. For residents concerned about water supplies and nearby development, the report is the next scheduled chance to inspect statewide findings.

From the source record

ERCOT impact inquiryData centers seeking at least 25 MW
ERCOT is issuing an RFI to obtain this information from all developers of data centers 25 MW or more that are pursuing interconnection to the ERCOT System.
ERCOT ↗
ERCOT’s inquiry covers large data-center proposals seeking grid connections.
How they votedComal County Commissioners Court, May 14, 2026
DecisionResultCount for–againstVoted no or abstained
Action Agenda Item 17Approve Resolution 2026-12 asking the state to examine impacts of additional data centersComal County Commissioners Court minutes, May 14, 2026, Action Agenda Item 17 ↗PassedNo count in the recordNot in the record
How each member voted
For (4)
Doug Leecock, Kristen Hoyt, Kevin Webb, Jen Crownover

Counts and names are shown only where the official record states them.

What the state is asking

ERCOT sent its inquiry to 465 loads and had received 433 responses as of Nov. 5. The preliminary update says those responses represent about 97% of the requested interconnection capacity covered by the inquiry. Those are requests to connect to the grid, not operating data centers.

ERCOT seeks information from developers of data centers requesting at least 25 megawatts of grid capacity. Its questions cover water sources and consumption, cooling, grid dependence, public assistance, and effects such as noise, light and traffic.

Why Comal County is watching

The county resolution asks state officials to study water use, power demand, tax incentives and effects on surrounding communities. The May 14 minutes show Judge Kristen Hoyt and Commissioners Doug Leecock, Kevin Webb and Jen Crownover voting for it; Commissioner Scott Haag voted against it.

New Braunfels separately developed data-center zoning rules. The city’s Nov. 16 file scheduled a second and final reading; Comal.News subsequently reported the council’s final decision in its New Braunfels data-center ordinance report. That city decision is separate from ERCOT’s statewide inquiry.

Texas Public Radio first reported the statewide story. ERCOT says it intends to publish its report by Dec. 10. Residents can check ERCOT’s impact-inquiry page then for the findings and whether they answer the water-use questions Comal County raised.

The Comal Daily

Comal County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.