Open site navigation
Explore Comal.News
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County news deskLocal reporting, every day

New Braunfels Approves Waterway Lane Trail Funding Deal

The $3.66 million shared-use path would connect Gruene Road and FM 306; construction is expected to start in May 2028.

Listen to this articleComal.News narrated edition
Ready · 0:00 / 2:44
An illustrated map marked with a dotted route lies beside unfinished trail segments winding through a cream, navy and muted-blue Hill Country landscape.
Illustration: A mapped route and emerging trail wind through the New Braunfels landscape.Original editorial illustration; not a photograph and does not depict the reported event or an exact property.Comal.News Visual Desk · Original illustration · Source ↗ · Comal.News original illustration ↗

Council approved item N. The approved resolution authorizes the city manager to enter the Waterway Lane Trail funding agreement.

The agreement advances an off-roadway shared-use path between Gruene Road and FM 306, with ADA curb ramps, a pedestrian hybrid beacon, seating and pedestrian lighting.

The project is estimated at $3,659,475. The funding plan assigns $2,914,400 to federal participation, $16,475 to the state and $728,600 to New Braunfels. The city also accepts responsibility for every cost overrun.

From roadway concept to trail

In 2021, New Braunfels studied a roadway in the Waterway Lane right-of-way; after residents opposed it, the city pursued a shared-use path and backed a grant application in January 2025.

The Texas Transportation Commission awarded funding in November 2025. The agreement says federal participation will cover 80% of eligible design and construction costs, up to the approved amount; New Braunfels pays its nonfederal share and costs above the cap.

A resident supported the Waterway Lane route as an off-street connection in a larger walking and bicycling network and cited outside funding covering 80 percent of its cost.

The approval is the material change since Comal.News reported the proposed agreement before the meeting. The earlier report explains how the projected local share is divided between design, construction and direct state costs.

What happens next

Construction is expected to begin in May 2028, and the city will decide how to fund its construction share after design is complete.

Park District 1 has enough money for the $131,800 design and direct-state-cost share, according to the city’s item report. The agreement requires a $59,800 payment to TxDOT within 30 days after execution.

The next useful records will be the executed agreement, completed design and the city’s construction-funding decision. Readers can use file 26-1037 in the official item record to track those documents and any revised project estimate.

From the source record

ADVANCE FUNDING AGREEMENTWaterway Lane Trail
The estimated total participation by Local Government is $728,600. The Local Government is responsible for 100% of overruns.
Texas Department of Transportation and City of New Braunfels ↗
The draft advance funding agreement sets the project scope, estimated cost shares and local responsibility for overruns.

Related coverage

The Comal Daily

Comal County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.