Open site navigation
Explore Comal.News
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County news deskLocal reporting, every day

NBU budgets $5.34 million to rehabilitate two existing water tanks

NBU has budgeted rehabilitation of its existing Kerlick and Newks water tanks for completion by July 2027. The planned work targets storage already serving water customers; a Kerlick filing is in review.

Listen to this articleComal.News narrated edition
Ready · 0:00 / 4:22
Two elevated water tanks stand in a sparse landscape with low hills, shrubs, and a cream sky.
Two elevated water tanks represent existing storage planned for rehabilitation; this does not depict the reported work.Illustration: Comal.News

NBU has budgeted about $5.34 million to rehabilitate two existing elevated water tanks, with most of that money set aside for contract labor.

For NBU water customers, the planned investment is rehabilitation of existing water storage. The capital plan places the Kerlick and Newks spending in fiscal 2027. NBU says its board approved that year's capital budget on June 25, 2026; later years are estimates. These figures are budgeted spending, not money already spent.

Contract labor accounts for most of the planned tank spendingApproximate FY2027 dollars
Source: NBU FY2027–FY2031 Capital Improvement Plan, Kerlick and Newks tank rehabilitation project.The bars show planned spending categories, not contract awards or actual expenditures.

What will NBU spend on Kerlick and Newks?

NBU describes the Kerlick and Newks work as full rehabilitation of existing elevated storage tanks and labels it aging infrastructure. The project concerns storage already in the water system.

Contract labor takes the largest share of the planned spending, followed by contract engineering, overhead and internal labor. The table gives each budget category's amount. Those figures do not establish the price of an awarded contract.

NBU's planned Kerlick and Newks tank rehabilitation spending, FY2027
Budget categoryPlanned amount
Contract labor$4,054,778
Contract engineering$622,053
Overhead$524,899
Internal labor$137,107

The plan states a $5,338,838 project total; its displayed component figures add to $1 less.

What does the spending mean for customers?

The project covers existing tanks rather than a new source of water. Its budget shows what NBU plans to spend on rehabilitation, but it does not set a charge for any individual customer.

NBU describes customer rates and utility revenues as support for capital work and debt payments across the utility. That systemwide funding explanation does not establish how NBU will finance this particular project or what share, if any, appears on a household bill.

What happens next?

The project entry gives an Aug. 1, 2025, start date and schedules completion for July 31, 2027. Its expenditure table puts the planned spending in fiscal 2027 and shows zero for fiscal 2028 through 2031. Those dates do not specify when a contractor will work at either tank.

New Braunfels' planning record shows a Kerlick Elevated Storage Tank tree-removal application filed Oct. 6, 2026, with its status listed as in review that day. The filing marks a step in the city's review; it does not establish that tank work has begun or that customers face an interruption.

A bid award, work order or construction schedule could establish the contract price and work dates. Readers can inspect Kerlick filing PL26-0359 in the city's public search portal and compare it with the project's spending schedule.

Related coverage

The Comal Daily

Comal County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.