Open site navigation
Explore Comal.News
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County news deskLocal reporting, every day

NBU budgets $14 million for Solms water replacement; full project cost runs higher

NBU plans to replace its Rusch Lane water facilities with a Solms pump station and 1-million-gallon tank. Its FY2027 budget includes $8.2 million; how the full project cost translates to customer bills remains an open financing question.

Listen to this articleComal.News narrated edition
Ready · 0:00 / 5:17
Line illustration of a large cylindrical water tank connected by an underground pipe to a small pump building in a pale, grassy landscape.
A conceptual water tank and pump station, representing the planned Solms replacement project rather than an observed site.Illustration: Comal.News

NBU's Solms water project has two price tags: about $14 million in its five-year plan and $20.6 million on its public project page.

The plan would replace the Rusch Lane pump station and tank with a new Solms station and a one-million-gallon tank at NBU's new headquarters. NBU's plan projects completion for July 31, 2028.

Contract labor accounts for most planned Solms spendingMillions of dollars, FY2027–31 plan
Source: NBU FY2027–31 Capital Improvement Plan, project 2-C20SLGST, p. 28.Values convert the plan's dollar figures to millions; displayed amounts are rounded.
Map

Where and when

The places and times below come from the official pages linked with each one.

What the two totals cover

The smaller number covers planned spending, not the estimated cost of the whole job. NBU's FY2027 capital budget includes about $8.2 million for Solms, and its FY2028 forecast adds about $5.8 million. Together, those years make up the five-year plan total. The separate rates page labels a higher figure as the project's projected cost.

Four different measures of Solms project cost and timing
MeasureAmountWhat it describes
FY2027 adopted capital budget$8,191,439Approved budget year
FY2028 forecast$5,804,146Planned later-year spending
FY2027–31 total$13,995,585Five-year plan window
Public project estimate$20.6 millionProjected whole-project cost

Sources: NBU FY2027–31 Capital Improvement Plan, project 2-C20SLGST, p. 28; NBU Your Rates at Work project listing.

NBU's board approved the FY2027 capital budget on June 25, 2026. The FY2028 amount remains a forecast. The larger whole-project estimate is neither an awarded contract nor a charge on a customer's bill.

Who pays for the replacement?

NBU's capital plan describes several funding sources across its system: debt, revenues and available funds, impact fees, Texas Water Development Board funding, and contributions or grants. For FY2027, the utilitywide plan lists $190.1 million in debt funding out of $244.2 million in total capital funding. The five-year figures are $503.3 million in debt and $899.6 million in total planned capital investment. Those systemwide numbers show how NBU expects to finance its broader building program; they are not a Solms-specific financing schedule.

A capital budget authorizes near-term spending. A financing schedule would show which funds pay for Solms and when debt payments come due. Calculating a cost per customer would also require the rates and customer assumptions applied to that financing. The public rates page says the second year of NBU's existing two-year rate plan took effect Aug. 1, 2026; it does not assign a Solms charge to a water bill.

What changes next

NBU's plan lists Aug. 1, 2019, as the project's start date. A city permit record dated Sept. 30, 2026, lists a post-approval plan change for the Solms pump station and ground storage tank as IN REVIEW. That permit status applies to the plan change; it does not establish that the new station or tank is operating.

The next useful checks are NBU's capital-budget updates, any project authorization amendment and the commissioning record for project 2-C20SLGST. Readers can find the current spending schedule under that project number in the capital plan and look for the record that reconciles the five-year spending window with the whole-project estimate.

Related coverage

The Comal Daily

Comal County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.