NBU's Solms water project has two price tags: about $14 million in its five-year plan and $20.6 million on its public project page.
The plan would replace the Rusch Lane pump station and tank with a new Solms station and a one-million-gallon tank at NBU's new headquarters. NBU's plan projects completion for July 31, 2028.
Where and when
The places and times below come from the official pages linked with each one.
- Site
Solms Pump Station and Ground Storage Tank
5802U IH35 S, New Braunfels
Address listed in city permit CP2025-824R.
What the two totals cover
The smaller number covers planned spending, not the estimated cost of the whole job. NBU's FY2027 capital budget includes about $8.2 million for Solms, and its FY2028 forecast adds about $5.8 million. Together, those years make up the five-year plan total. The separate rates page labels a higher figure as the project's projected cost.
| Measure | Amount | What it describes |
|---|---|---|
| FY2027 adopted capital budget | $8,191,439 | Approved budget year |
| FY2028 forecast | $5,804,146 | Planned later-year spending |
| FY2027–31 total | $13,995,585 | Five-year plan window |
| Public project estimate | $20.6 million | Projected whole-project cost |
Sources: NBU FY2027–31 Capital Improvement Plan, project 2-C20SLGST, p. 28; NBU Your Rates at Work project listing.
NBU's board approved the FY2027 capital budget on June 25, 2026. The FY2028 amount remains a forecast. The larger whole-project estimate is neither an awarded contract nor a charge on a customer's bill.