NBU plans a $6.21 million Comal Substation upgrade, but only the first $82,107 is in its approved FY2027 capital budget.
The FY2027 capital budget was approved June 25, 2026, while FY2028–FY2031 figures remain planning estimates subject to future board action. That makes the project’s headline cost a plan, not a single approved construction contract.
Where and when
The places and times below come from the official pages linked with each one.
- Site
Comal Substation
Comal Substation
Target completion July 31, 2029
Project 1-C27COHLF in NBU’s capital plan
Where the money lands
The plan schedules $82,107 in FY2027, $262,408 in FY2028 and nearly $6 million in FY2029, for $6,209,002 in all. The 2029 forecast carries by far the largest outlay. The table separates the approved current-year amount from later planning figures.
| Fiscal year | Planned spending | Status in the capital plan |
|---|---|---|
| FY2027 | $82,107 | Approved capital budget |
| FY2028 | $262,408 | Planning estimate |
| FY2029 | $5,864,487 | Planning estimate |
| FY2030–FY2031 | $0 | No spending scheduled |
NBU says FY2028–FY2031 estimates require future board action.
NBU divides the projected cost into $2.6 million for contract labor, $2.6 million for materials, $609,002 for overhead and $400,000 for contract engineering. Those categories describe the planned project budget; the fiscal-year table shows when NBU expects to spend it.