NBU budgeted about $700,000 next year for the smaller Comal Substation job, but just $82,000 for the larger one. Why does the smaller job get more now?
The Torrey Street feeder move and Transformer 3 replacement are in the adopted FY2027 budget, while most spending on the larger Comal Substation configuration is forecast for FY2029. The jobs have different schedules and different equipment.
Why does the smaller job get more money now?
The adopted FY2027 budget assigns about $700,000 to project 1-C24COT3, which replaces Transformer 3, moves the Torrey Street feeder and converts associated connections underground. NBU's five-year capital plan gives that work a Dec. 31, 2027, completion date.
The other project, 1-C27COHLF, calls for six breakers and four 138-kilovolt terminals with LCRA Transmission Services. Its listed completion date is July 31, 2029. Those are different equipment lists and different schedules at the same substation.
Our earlier Comal Substation report follows the larger project's spending schedule. The useful comparison here is between the adopted budget for each job and the later forecast for the larger one.