Schertz is weighing a $894,164 bid from RL Jones for a 12-inch water main along IH-10 from Graytown Road to Pfeil Road, with a proposed contract ceiling of $1 million.
The planned 12-inch main would replace an undersized 2-inch line and create a loop intended to improve redundancy for water customers. The proposal is Resolution 26-R-108 in the city’s Oct. 13 council packet.
The city describes the existing segment as an undersized 2-inch water line. That makes the proposed work a service-reliability project as well as a construction purchase. The packet says a separate Lower Seguin Road-to-Ware Seguin Road segment is awaiting an easement and would be bid separately. The price now before council covers the Graytown-to-Pfeil work, not that later segment.
Five prices—and two different bid counts
The five tabulated bids are RL Jones at $894,164; Nelson Lewis at $1,085,305.70; Guerra Underground at $1,152,429.26; E-Z Bel at $1,260,831; and Qro Mex at $1,672,482. The engineer’s estimate, including contingency, is $1,455,137.02. These figures put the low offer below both the other bids and the estimate, but they do not establish why RL Jones priced the work as it did.