The Portillo's proposal now has a defined 4,987-square-foot drive-through plan at 2807 Sophie Lane and a completed state accessibility review, while New Braunfels still lists its building application as IN REVIEW.
The state record lists Nov. 2, 2026 as Start Date and May 3, 2027 as Completion Date, but city review remains unfinished and neither record supplies a customer opening date.
A drive-through plan with a specific footprint
TABS2026025141 was registered July 13 and displayed Review Complete when checked directly Aug. 28. Its scope calls for ground-up construction of a commercial restaurant with a drive-through, associated site work and landscaping. The filing's Estimated Cost field is $2.5 million, it names Portillo's Hot Dogs as the facility, and it uses the same Sophie Lane address found in the city record.
One project, two separate reviews
The state accessibility record and the city building application answer different questions; one status cannot stand in for the other. Review Complete is a checkpoint in Texas' architectural-barriers process, which includes registration, plan review and an inspection after construction. The project page says the owner must request that inspection once construction is finished. It does not finish the local building process.