NBU has adopted just $82,107 for a Sheriff's Posse substation expansion whose full plan reaches nearly $9 million.
A Comal.News calculation from NBU's capital plan puts $8,909,256—99.09% of the $8,991,363 project total—in the FY2028–FY2030 forecast years. Those later amounts are planned spending, beyond the adopted FY2027 project line.
For NBU electric customers, the plan puts most spending on this capacity project in future budgets, beyond the adopted FY2027 project line. The distinction matters because the large construction years still lie ahead; the project total is not a charge on a household bill.
What the planned $9 million buys
NBU describes project 1-C27SPT3 as an expansion of Sheriff's Posse Substation with a third transformer rated 20/26.6/33.3 megavolt-amperes. It also plans to procure land from Sheriff's Posse Arena. The equipment rating describes the proposed transformer; it does not establish how much additional power a particular neighborhood will receive.
The project's largest estimated cost is materials, at $4.19 million. It also lists $2 million for contract labor and $900,000 for land and easements. The cost categories describe the whole project, while the annual schedule shows when NBU expects to spend the money.