Open site navigation
Explore Comal.News
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County, TexasUpdated throughout the day
Local intelligence for a fast-growing county
Send a tip

The Comal Daily

Comal County, before your second cup.

Comal County news every morning, with links to the original sources.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.
Comal County news deskLocal reporting, every day

NBU plans $7.81 million River Chase tank replacement, with most spending after 2029

River Chase water customers are slated for a 500,000-gallon replacement tank and connecting main. NBU has adopted $292,043 for FY2027; later spending remains planned.

Listen to this articleHear this story read aloudComal.News narrated edition
Ready · 0:00 / 5:14
An illustrated plan shows an elevated water tank connected to a pipe, with two pipe sections and a pencil nearby.
A planned water tank and connecting main, shown as a conceptual drawing rather than a depiction of the River Chase site.Illustration: Comal.News

River Chase’s planned replacement tank carries a $7,807,374 five-year price tag, but NBU has adopted $292,043 for FY2027.

NBU plans a 500,000-gallon elevated replacement tank and about 8,000 feet of 16-inch main connecting it to the River Chase Pressure Zone. For water customers in that zone, the pipe connection is part of the project itself, alongside the tank.

Contract labor is the largest planned River Chase costDollars, FY2027–FY2031 project estimate
Source: NBU FY2027–FY2031 Capital Improvement Plan, project 2-C26RCEST, printed p. 39.

The capital plan marks FY2027 as adopted; its FY2028–FY2031 figures are planning estimates subject to review and Board action. That distinction matters more than the big five-year total: the later figures describe a schedule NBU can revisit, not money already authorized for every year.

What does the plan buy?

The project description pairs storage with a connection to the named pressure zone. Those are concrete pieces of water infrastructure. The 500,000 gallons describe the planned replacement tank’s capacity; the plan does not turn that number into a promised increase in storage or a measured improvement in service.

NBU lists August 1, 2026, as the project start and July 31, 2031, as projected completion. The date is a target for the project, not a date on which customers are promised a new tank in service.

Most of the spending lies ahead

The largest listed annual project expenditure is $4,486,385 in FY2031. FY2028 carries no planned project expenditure, followed by an increase in the estimates for FY2029 and FY2030. The table shows why the adopted FY2027 amount is a small part of the full plan.

River Chase tank project expenditures in NBU’s FY2027–FY2031 plan
Fiscal yearListed expenditureStatus
FY2027$292,043Adopted
FY2028$0Planning estimate
FY2029$638,800Planning estimate
FY2030$2,390,145Planning estimate
FY2031$4,486,385Planning estimate

The plan prints a five-year total of $7,807,374; its displayed annual amounts add to $7,807,373, a $1 difference.

NBU’s FY2027 Financial Operating Plan repeats the River Chase project’s annual expenditure schedule. The agreement between the two plans confirms the spending profile, while future Board reviews still govern the years beyond FY2027.

What to watch next

The five-year estimate assigns $4.5 million to contract labor, $1,181,447 to contract engineering, $1,706,426 to overhead, $250,000 to land and easements, and $169,500 to labor. Construction work is the largest listed cost, but a project budget is not a household water-rate calculation.

The next annual capital-plan review is the decision point for spending beyond the adopted FY2027 amount. Readers can track project 2-C26RCEST in NBU’s capital plan, then compare later Board-approved budgets and contract records with this schedule.

The Comal Daily

Comal County, before your second cup.

A clear morning briefing, with direct links to the records and sources behind each story.

By subscribing, you agree to receive The Comal Daily and to our Terms and Privacy Policy. Unsubscribe anytime.