NBU's capital plan puts $5.38 million toward rehabilitating the Mission Hills Ranch and Gruene Road elevated tanks, with most of the money forecast for FY2028.
FY2027's adopted capital budget sets $525,678 for the project; nearly $5 million is forecast for FY2028. That larger amount is a planning estimate, not money budgeted for FY2027.
Where the $5.38 million goes
The planned work concerns two existing elevated water tanks named Mission Hills Ranch and Gruene Road. NBU describes the project as a full rehabilitation of the tanks; the spending lines show how it expects to pay for the work, rather than a separate cost for each tank.
Contract labor alone accounts for $3.5 million of the FY2028 forecast. Contract engineering is the largest FY2027 line, at $460,495. Look at the contract-labor row: that is where the spending shifts sharply between the adopted year and the forecast year.
| Cost category | FY2027 adopted | FY2028 forecast |
|---|---|---|
| Internal labor | $13,500 | $127,500 |
| Contract engineering | $460,495 | $837,436 |
| Contract labor | $0 | $3,500,000 |
| Overhead | $51,683 | $394,079 |
| Total | $525,678 | $4,859,015 |
Project 2-C27WTRP3, printed p. 37 of NBU's FY2027–FY2031 capital plan. FY2028 is a planning forecast.