NBU plans to put about $10.8 million into a substation near FM 3009 and SH 46, but its first approved year accounts for only about $1.2 million. Most of the planned spending would come later.
Only the FY2027 share has been appropriated; the FY2028 and FY2029 amounts are planning estimates subject to later review and board action. The NBU FY2027–2031 capital plan sets out the project and its spending schedule.
The planned design would add two power transformers, six feeders and three connections to existing electric infrastructure near FM 3009 and SH 46. NBU describes it as its planned 12th distribution substation.
How much capacity would FM 3009 get, and who would receive it?
The equipment count shows how NBU proposes to build out the station. It does not, by itself, translate into a count of customers served. A feeder service map and engineering load forecast would make the connection between the planned hardware and the streets or developments using it.
What the spending schedule shows
The plan's three-year spending schedule totals about $10.8 million. FY2028 carries the largest annual estimate, followed closely by FY2029; the approved FY2027 amount covers a smaller first stage. The table keeps that approved amount separate from the later forecasts.