Comal ISD postponed the Elementary 21 guaranteed maximum price decision on Oct. 22 after administrators requested more data.
The board also approved naming the building that will house the new Life Bridges East facility the Dan Krueger Building, 6-0.
From the source record
Item 6F, approval of the guaranteed maximum price (GMP) for Elementary 21, was pulled from the consent agenda and postponed at the administration's request for more data.Comal ISD verified meeting outcome ↗
Elementary 21 price decision
At its Oct. 22 meeting, the Comal ISD board approved its consent agenda as amended, with the Elementary 21 guaranteed maximum price item removed, 6-0. The price item was postponed at the administration's request for more data. A later board record will show when the proposal returns.
Life Bridges East naming
The board's 6-0 naming decision honors former trustee Dan Krueger. It names the building planned to house the new Life Bridges East facility; the retained outcome does not supply a separate construction-price decision for that facility.
An earlier Schertz decision
In a separate action on Oct. 13, Schertz City Council approved a 4% raise for City Manager Steve Williams and a one-year contract extension following his annual evaluation, 7-0. That decision occurred before the Oct. 18–24 week covered by the Comal ISD actions above. Readers can inspect the Schertz council meeting video for that earlier action.