County annual reports have shifted the projected construction finish for Comal County's crisis facility from fall 2025 to the end of 2026.
The Nov. 24 agenda asks commissioners to replace a previously approved $50,400 Bath Group commissioning proposal with $56,186 for Command Commissioning LLC. That is $5,786 more, about 11.5% above the earlier commissioning price; the comparison is between service proposals, not the facility's total cost.
From the source record
The facility is estimated to be completed by the end of 2026.Comal County FY2025 Annual Comprehensive Financial Report ↗
The projected construction finish does not itself establish when residents can receive care at the unit. The county describes the project as an extended observation and crisis residential facility; finishing the building and beginning clinical service are separate milestones.
Where and when
The places and times below come from the official pages linked with each one.
- Venue
Commissioners Courtroom
100 Main Plaza, New Braunfels
Nov. 24, 2026, 8:30 a.m.
How the target moved
The FY2023 report projected a fall 2024 construction start and fall 2025 completion. The FY2024 report then projected an April 2025 start and completion in early 2026. Both dates estimated construction, not an opening for patients.
| County report | Construction start | Projected completion |
|---|---|---|
| FY2023 | Fall 2024 projected | Fall 2025 projected |
| FY2024 | April 2025 projected | Early 2026 projected |
| FY2025 | Began in 2025 | End of 2026 projected |
These are construction projections, not dates for clinical service.